Presentation Issues: It seems that the fire alarm was triggered sometime over night — all of the servers were on red-light mode when I came in. I did the rounds of the building and re-set the override in each booth. Everything was fine from then on.

** both evening shows in theater 2 (Vice and The Favourite) failed to auto-start and had to be run manually

*** the final show in theater 7 (Vice) also failed to auto-start and had to be started manually

Preshow Clips/Playlist: scheduled the rest of Thursday's shows where possible (beware of a few manual starts in there)

Trailer Updates:

Special Events/ AV set up:

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content): we received KDMs for Glass. They have been uploaded to all screens — feature should be good to go (it's reading as playable in Thursday's scheduler)

** we did also eventually get the updated Green Book keys for tomorrow & Thursday. These have been ingested and are good to go.

Outgoing/Shipping (content): a courier was supposed to arrive to pick up our drive of Green Book. I never received any word that they were on premises, but, the drive is sitting in booth 4/6 if it still needs to be picked up.

Print/video Inspection:

Distro Doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated (only if needed):

Showtime boards & recording updated?:

Cleaning lights on for the night?: Yep