To do this evening/ was completed: Jerry from DMS was on site with a coworker to fix the sound/changeover issue in 4/6. Update: They fixed the sound switch issue in 4 but had to troubleshoot the dowsers rising/dropping in sync with the changeover cue; Jerry took a part from a projector in 2 to try to fix this. Tested reel 1 of Fear in 6; Jerry switched channels from 7.1 to 5.1 and there was still no sign of any buzzing noise from the rear surround speakers. Jerry left around 4:30, said he would have to return to continue working on the changeover/dowser problem in 4.

Presentation Issues:

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Tested mics in 4/6. All mics are functional and levels are good (vol 8.0). XLR cables are attached to the backs of the sound processors (in the booths) for both auditoriums. Replaced old batteries in the spotlights and spotlight remote for 6.

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content): Received a 35mm print of Dogtown and Z-Boys and a DCP of The Muppet Movie.

Outgoing/Shipping (content):

Print/video Inspection: Tested Night of the Living Dead DCP in 1; the feature is scoreless but all the dialogue is synced and picture looks great. Credit/crawl timestamps and additional DCP information was written in the asset tracking log.

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift):

Marquee updated?: Letters for Gothika and Fear were placed on the 14th street side of the building along with their corresponding screening dates.

Posters updated?:

Cleaning lights on for the night?:

Projectors off for the night?:

Projection cart by TH5?:

Nest:

Additional Notes: