NPP Projection Report 3/13 Admin
To do this evening/ was completed:
Presentation Issues: AC Blower interlock alarm in theater 1; hard reboot fixed this. Flicker in theater 5 wall light is back but the light is still functional since it was just replaced
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: Fist of Legend screening in theater 1 went smoothly
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content):
Outgoing/Shipping (content): Brought the Fist of Legend print and Chopping Mall DCP to the cart for Jack to leave by 3/7 for tomorrow's pickup
Print/video Inspection:
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift):
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projectors off for the night?:
Projection cart by TH5?:
Nest:
Additional Notes: Daylight savings seemed to have an effect on the TMS today as all scheduled showtimes were pushed forward an hour; I had to pull back each playlist for the shows to start at the correct times (Has this been an issue or ever occurred in the past? The sales page and cue sheets were accurate despite the technical glitch)
Presentation Issues: AC Blower interlock alarm in theater 1; hard reboot fixed this. Flicker in theater 5 wall light is back but the light is still functional since it was just replaced
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: Fist of Legend screening in theater 1 went smoothly
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content):
Outgoing/Shipping (content): Brought the Fist of Legend print and Chopping Mall DCP to the cart for Jack to leave by 3/7 for tomorrow's pickup
Print/video Inspection:
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift):
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projectors off for the night?:
Projection cart by TH5?:
Nest:
Additional Notes: Daylight savings seemed to have an effect on the TMS today as all scheduled showtimes were pushed forward an hour; I had to pull back each playlist for the shows to start at the correct times (Has this been an issue or ever occurred in the past? The sales page and cue sheets were accurate despite the technical glitch)
Comments