To do this evening/ was completed:

Presentation Issues: During the pre-show before the Born to Win screening in theater 4 I tested the changeovers and noticed the changeover gate on projector 1 was not raising up whenever I pressed the button to trigger it to switch. Alec was present to watch the film and came up to the booth to look over everything with me. He saw that the audio was switching from projector to projector despite the gate being locked in the down position so I rebooted everything and tried the buttons again but the gate on 1 still would not raise up. Due to this, I ran the first reel from projector 2 and, whenever I had to switch to the opposite side, lifted the changeover plate by hand as I triggered the other plate to turn down

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Born to Win screening in theater 4 went smoothly; mic and mixer were left behind the curtain for tomorrow evening's introduction to Bug 

Ordering/Receiving (posters & trailers): Thor: Love and Thunder and Crimes of the Future posters were delivered and stored behind 3/7

Ordering/Receiving (content):

Outgoing/Shipping (content):

Print/video Inspection: Finished inspecting Ricochet; re-inspected Born to Win and wound it back onto its shipping reels

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift):

Marquee updated?:

Posters updated?:

Cleaning lights on for the night?: Yes

Projection cart by entrance?: Yes