To do this evening/ was completed: Uploaded Jade print stills to Google Drive, emailed Conrad. Do we have more of these? I only uploaded three.

Presentation Issues: Roger from CTS came by to check out the sound issues in T1. He manually tested the EQ and determined that the levels on P2 were fine, but the optical barrel on the soundhead wasn't focused and the azimuth was "off", which means you'll start to hear dialogue coming out of the surround speakers. Ultimately said it was a frequency response that Alec was hearing and the only way to know it's fully resolved is to listen to another changeover, but he was satisfied with the changes he made. P1's EQ was perfectly balanced, he said.

As Roger was teching in 1, I was checking out P1 in T4 and noticed that the pad shoe was much looser than the one on P2. I had Roger tighten it then ran a reel to see if I could replicate the side to side movement I saw yesterday. The frame was steady, however during reel 4 of the actual show (DEBS) there was a bit of a side to side jitter during some shots. I also noticed that when I would adjust focus on this projector the whole frame moved side to side very easily, so something might be up with the knob.

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: DEBS screening went smoothly.

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content):

Outgoing/Shipping (content):

Print/video Inspection:

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift):

Marquee updated?: Took down DEBS letters.

Posters updated?:

Cleaning lights on for the night?:

Projection cart by entrance?:

Additional Notes: Was 15 minutes late due to irregular train service.