To do this evening/ was completed:

Presentation Issues:

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Shouting at the Screen went very well, all cables, mics, the mixer, and other miscellaneous equipment is back in 4/6. The wireless mics are back in Theater 2’s booth. PA speakers and their stands remain behind the curtains in Theater 2 as Theater 1 was still in the middle of a show when I left.  The DJ equipment was broken down and cables returned to 4/6 however it needs to be stored in the closet before opening tomorrow.

Ordering/Receiving (posters & trailers): 

Ordering/Receiving (content): Bullet Train DCP arrived, ingested to TMS and all IMS servers.

Outgoing/Shipping (content): Printed a shipping label for Lilya 4-Ever and scheduled a pickup for tomorrow. Placed the print on the cart.

Print/video Inspection: I did not get to inspecting any more of Malcolm X. I wound the 7th reel back onto the shipping reel and placed it in the can.

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift): Checked cue sheets/schedule for Saturday and Sunday. Updated the credits for the playlists which ended up being a minute shorter on those two days’ cues, as well.

Marquee updated?:

Posters updated?:

Cleaning lights on for the night?: Yes

Projection cart by entrance?: Yes

Additional Notes: