NPP Projection Report 7/28 Close
To do this evening/ was completed:
Presentation Issues:
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: Shouting at the Screen went very well, all cables, mics, the mixer, and other miscellaneous equipment is back in 4/6. The wireless mics are back in Theater 2’s booth. PA speakers and their stands remain behind the curtains in Theater 2 as Theater 1 was still in the middle of a show when I left. The DJ equipment was broken down and cables returned to 4/6 however it needs to be stored in the closet before opening tomorrow.
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Bullet Train DCP arrived, ingested to TMS and all IMS servers.
Outgoing/Shipping (content): Printed a shipping label for Lilya 4-Ever and scheduled a pickup for tomorrow. Placed the print on the cart.
Print/video Inspection: I did not get to inspecting any more of Malcolm X. I wound the 7th reel back onto the shipping reel and placed it in the can.
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Checked cue sheets/schedule for Saturday and Sunday. Updated the credits for the playlists which ended up being a minute shorter on those two days’ cues, as well.
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?: Yes
Projection cart by entrance?: Yes
Additional Notes: