NPP Projection Report 9/27 CLOSE
To do this evening/ was completed: Yes
Presentation Issues: When setting up Trivia, the first mic input wasn't working. After some troubleshooting with Alec, I tried switching over to the second mic input and that worked. Alec is going to take a look at it all tomorrow morning.
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: The private screening of My Best Friend's Exorcism went great. Alec walked me through mic set up and break down when the host didn't need a mic. Transition from the intro into the feature went smooth.
Once the sound hiccup with was sorted out, Trivia went nicely as well.
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Ham On Rye finished downloading, so I put it on the drive and tried to upload it to the Theater 3 server. It wasn't recognizing the DCP, so something may have happened in the download. But I left the DCP drive on the iMac station.
Outgoing/Shipping (content):
Print/video Inspection:
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Yes. I observed Alec updating the cue sheets for next week.
Marquee updated?:
Posters updated?: Updated the trivia posters that were given out.
Cleaning lights on for the night?: Yes