NPP Projection Report 9/27 CLOSE



To do this evening/ was completed: Yes 

Presentation Issues: When setting up Trivia, the first mic input wasn't working. After some troubleshooting with Alec, I tried switching over to the second mic input and that worked. Alec is going to take a look at it all tomorrow morning. 

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: The private screening of My Best Friend's Exorcism went great. Alec walked me through mic set up and break down when the host didn't need a mic. Transition from the intro into the feature went smooth. 

Once the sound hiccup with was sorted out, Trivia went nicely as well. 

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content): Ham On Rye finished downloading, so I put it on the drive and tried to upload it to the Theater 3 server. It wasn't recognizing the DCP, so something may have happened in the download. But I left the DCP drive on the iMac station.  

Outgoing/Shipping (content):

Print/video Inspection:

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift): Yes. I observed Alec updating the cue sheets for next week. 

Marquee updated?:

Posters updated?: Updated the trivia posters that were given out. 

Cleaning lights on for the night?: Yes 

Projection cart by entrance?:

Additional Notes: