NPP Projection Report 9/29 Close

To do this evening/ was completed:

Presentation Issues: The last round in theater 2 did not start as scheduled and was delayed five minutes after I started the show playlist manually; I skipped ahead in the playlist to compensate for the delay 

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: The screening of Zodiac in theater 1 went very smoothly; I rewound all nine reels (these are heads out and ready for inspection again tomorrow) and cleaned both projectors after the show

Ordering/Receiving (posters & trailers): Empire of Light and Lyle, Lyle, Crocodile one sheets were delivered and stored behind 3/7 in the poster cubby; I discarded a few poster tubes that had taken on damage in transit and reorganized the few that were in better shape

Ordering/Receiving (content):

Outgoing/Shipping (content):

Print/video Inspection:

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift):

Marquee updated?:

Posters updated?:

Cleaning lights on for the night?: Yes

Projection cart by entrance?: Yes

Additional Notes: I was unable to make any progress converting the NewFest short film files to DCPs as I did not have access to the GoogleDocs spreadsheet with the download links for most of the afternoon; the desktop was running very slowly for most of the day so I hesitated to begin any new conversion tasks after Lillian granted me access to the spreadsheet (by this time the Zodiac pre-show had begun so I moved downstairs to start preparing the projectors and reels for the screening)