NPP Projection Report 12/6 Close
To do this evening/ was completed:
Presentation Issues:
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: Barking Dogs Never Bite screening in theater 1 went well (had to raise the volume for the feature ever so slightly since the room was nearly full); Trivia at Trees Lounge, though modestly attended, went smoothly
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content):
Outgoing/Shipping (content):
Print/video Inspection: Took a look at the first half of Jackie Brown (reels 1-4) and the print is in mint condition despite needing grease cues added with, from what I could see, zero scratches throughout; I left the second half of the print for Alec and/or Lillian to inspect as they will be here tomorrow morning and since Alec is running the show on the 10th I figured he might like to see some of the film up close before projecting it
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift):
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?: Yes
Projection cart by entrance?: Yes
Additional Notes: The rain this evening caused some leaking in theater 6 (the majority of it was closer to the right hand side of the screen by the server entrance though it could also be heard hitting the ceiling tiles toward the back of the auditorium too) and outside in the hallway between the auditorium entrance door and the security camera by the elevator where a bubble had begun to form on the wall; MODs placed wet floor signs where necessary and this did not interfere with the presentation of the last round(s)
Presentation Issues:
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: Barking Dogs Never Bite screening in theater 1 went well (had to raise the volume for the feature ever so slightly since the room was nearly full); Trivia at Trees Lounge, though modestly attended, went smoothly
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content):
Outgoing/Shipping (content):
Print/video Inspection: Took a look at the first half of Jackie Brown (reels 1-4) and the print is in mint condition despite needing grease cues added with, from what I could see, zero scratches throughout; I left the second half of the print for Alec and/or Lillian to inspect as they will be here tomorrow morning and since Alec is running the show on the 10th I figured he might like to see some of the film up close before projecting it
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift):
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?: Yes
Projection cart by entrance?: Yes
Additional Notes: The rain this evening caused some leaking in theater 6 (the majority of it was closer to the right hand side of the screen by the server entrance though it could also be heard hitting the ceiling tiles toward the back of the auditorium too) and outside in the hallway between the auditorium entrance door and the security camera by the elevator where a bubble had begun to form on the wall; MODs placed wet floor signs where necessary and this did not interfere with the presentation of the last round(s)