To do this evening/ was completed:

Presentation Issues: The final round in theater 2 paused playback and was delayed by three minutes

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Ran loops for scope in theater 1 and cleaned both projectors prior to the screening of The Fan screening this evening (this went very smoothly; picture and sound were sharp throughout)

Ordering/Receiving (posters & trailers): Additional Dune 2 posters were delivered and stored behind 3/7

Ordering/Receiving (content): Continued converting NSF24 shorts content to DCP and copied all available files to the DCPII drive from the NSF one; these were ingested to the TMS this evening

Car Wash was delivered this afternoon and brought up to 4/6

Downloaded and ingested new keys for The Boy and the Heron

Yi Yi feature content became available this evening through EclairPlay and was ingested to the TMS

Outgoing/Shipping (content):

Print/video Inspection: Re-inspected The Fan following the screening and packaged it for return shipping along with Taxi Driver (both prints are on the cart for the Sony courier to receive them if a return is locked in for tomorrow)

Asset tracking doc updated/checked?:

Maintenance/cleaning: Swept up around booth 1 while setting up for The Fan

Cue sheets updated/checked (every shift): Yes (double checked against the schedule tab and website and initialed for confirmation); a single Poor Things OCAP show needed to be adjusted but has been fixed

Marquee updated?:

Posters updated?: Removed some titles from the trivia section and reorganized the cubby; removed Kung Fu Panda 4 from outside and replaced it with Argylle since it is opening sooner

Cleaning lights on for the night?: Yes

Projection cart by entrance?: Yes

Additional Notes: