NPP Projection Report 3/19 Close

To do this evening/ was completed:

Presentation Issues: Playlist paused before the final round in theater 6; manual start to the pre-show which was delayed by about 2 minutes

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Added additional digital event names/dates to the dry erase board in 4/6 for the final week of the month; began converting The Holy Mountain to DCP (DCP-o-Matic currently says it will take about 23 hours to finish)

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content):

Outgoing/Shipping (content):

Print/video Inspection: Spent the majority of the afternoon inspecting The Texas Chainsaw Massacre 2 and rewound all reels to their tails on shipping reels (reel 5 has some significant edge/perforation damage near its tail -- this was noted on the inspection report); also uploaded some stills to the shared drive

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift):

Marquee updated?:

Posters updated?:

Cleaning lights on for the night?:

Projection cart by entrance?:

Additional Notes: Multiple AC units throughout the building went down around 11PM; called MODs to reset them (unit in booth 2 was blowing hot air out and took a moment after being reset to start blowing cool air -- units in 1 and 4/6 were reset and began functioning normally)