To do this evening/ was completed: Dinosaurs/Subway/Scream preshow content downloaded and ingested. Scream and 65 playlists built. Started scheduling the upcoming week in TMS. T1 and 4/6 swept and mopped. Scarface removed from T3.
Presentation Issues: T1 shutdown struck the lamp off but dowser remained open. Just thought it was curious. T3 "light change recommended" when scheduled shutdown started.
Preshow Clips/Playlist:
Trailer Updates:
Special Events/ AV set up: Christine played smoothly, lots of laughs.
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content):
Outgoing/Shipping (content):
Print/video Inspection:
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Yes
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projection cart by entrance?: