To do this evening/ was completed: Somewhat busy morning. Handful of technical blips. First: T7 IMB was down when I got in. I tried to initiate a marriage through the Christie Service setup but could not click "next" to advance past the first prompt. So I decided to power-cycle the projector and that resolved the issue. Put Friendship on screen to test the server and it played fine. I did notice a relatively decent amount of empty space at the bottom of the image--the lens file just hadn't been expanded enough, so I adjusted it. All good. Plenty of time before the first round started.

Then I got walkie'd by MOD informing T2 preshow had started but the lights had not gone down--they remained on the CLEANING setting, so I just brought them down manually. Tested the all of the settings, they are fine and responsive. But I haven't experienced that specific T2 glitch before.

Then MOD forwarded an email from a patron saying that there was a loud, persistent rumbling/rattling coming from one of our speakers/subwoofers during MI8 yesterday. Apparently we received two separate complaints. So I put MI8 on-screen before the print and clicked around to listen to some action and yes, the JBL beneath the screen does rattle/buzz/rumble prominently during certain loud action sequences. I got some time stamps for further investigation: around/slightly after 1:421:30, and around 1:43:08. Was able to show MODs these moments, which is to say the issue is consistent.

And then, once the preshow for Batman Begins had begun I was informed that the image on-screen was being projected onto the curtains, even though the 1.85 lens file was selected. Looked at the Christie touch panel to see a "ballast power control locked..." alarm message, which I acknowledged, then simply re-selected 1.85 on the panel, which resolved the issue. Tested some content after the screening and everything worked fine.

Presentation Issues:

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Batman Begins + Dark Knight trailer went smoothly. Print is rewound for tomorrow. Projectors cleaned.

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content):

Outgoing/Shipping (content):

Print/video Inspection:

Asset tracking doc updated/checked?:

Maintenance/cleaning:

Cue sheets updated/checked (every shift):

Marquee updated?:

Posters updated?:

Cleaning lights on for the night?:

Projection cart by entrance?:

Additional Notes: