Projection Admin 7/9 (Didn't get posted! Yesterday morning's blog) Lillian
To do this evening/ was completed: In response to Will's blog last night, it looks like the playlists I made for Superman 7/04 (for 7/10 release date) were deleted and the 7/11 ones were copied over from F1, given everything that was in those incorrect Superman playlists from last night. there were updates earlier in the day, so please be be very careful if you are copying over to kill some time with not having to redo the trailers and such (if that was the intention). This is also why we double check the playlists. I still believe the template system might be too much for us here, but for right now, please be sure to double check your work. I am a tad concerned that Tuesday admin work has become slightly passive.
Also as per Will's blog, I checked out the faulty reel (reel one) of Nickel Boys which seemed to have multiple key pieces rolling around the core. I contacted Brad from Film Tech (in charge of this) and offered to tease them out but wanted to double check that this was, in fact, the last print for 2k reels available on the off chance they had another. They did not have another. He suggested trying to get it on the bench with a different spindle (along with a separate emergency plan for shipping) but the reel started to split the second I lifted it up. I was able to give it a pretty clean break, got a core in it for the split reel and then safely wound it onto a house reel without damaging it. They're alright for us to toss the reel, which lost most of its adhesive and got mucked up in the shipping process. All other shipping reels are okay. I have inspected the first two reels. If you're curious about this visually, I have the photos of the whole thing in the Photos app on 4/6 desktop. Everything went rather smoothly considering.
We've got some power issues in T1/2 server stations, which Juan was working on today. I noticed the new emergency lights in T1 were on (only three of them, though - Vlad is aware). Turns out, the breaker was wonky and a quick switch on/off worked. Matthew was here today and is aware of all of this, too. FYI- I ran through playlists/lights sequences to make sure the cleaning lights were all good for today.
Presentation Issues:
Preshow Clips/Playlist: Checked the Super 8 and Hank's Saloon playlists.
Staff Screening info out.
Trailer Updates:
Special Events/ AV set up: Setup the mic in T4 for Hank's Saloon tonight.
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Ingested Beverly Hills Cop and Peewee's Big Adventure
Outgoing/Shipping (content):
Print/video Inspection: We received the SOF print this evening, so please inspect the first reel of that as we are looking to tech it tomorrow. I brought it this up to T1.
Asset tracking doc updated/checked?:
Maintenance/cleaning: Ran loops and adjusted lenses/port glass tape for Super 8 this evening.
Cue sheets updated/checked (every shift): Yes
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projection cart by entrance?:
Additional Notes:
Trailer Updates:
Special Events/ AV set up: Setup the mic in T4 for Hank's Saloon tonight.
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Ingested Beverly Hills Cop and Peewee's Big Adventure
Outgoing/Shipping (content):
Print/video Inspection: We received the SOF print this evening, so please inspect the first reel of that as we are looking to tech it tomorrow. I brought it this up to T1.
Asset tracking doc updated/checked?:
Maintenance/cleaning: Ran loops and adjusted lenses/port glass tape for Super 8 this evening.
Cue sheets updated/checked (every shift): Yes
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projection cart by entrance?:
Additional Notes:
Comments
Post a Comment