NPP Projection Close 3/13
To do this evening/ was completed:
Presentation Issues:
Preshow Clips/Playlist: Ingested TLR_NPP_FORECAST_0313_A_V2 and updated this week's playlists accordingly
Presentation Issues:
Preshow Clips/Playlist: Ingested TLR_NPP_FORECAST_0313_A_V2 and updated this week's playlists accordingly
Built and scheduled an infants playlist for Sirāt this Tuesday 3/17 (pre-show, trailer, and feature volumes lowered + house lights at mid level for the duration of the trailers and film)
Built all first run show playlists for the week of 3/20 (with the exception of Project Hail Mary since we are waiting on the rest of its pre-show files) and a show playlist for Labyrinth on 3/21-22. A few special event pre-shows remain but can be built in the coming days as the majority of these do not screen for another week
Trailer Updates:
Special Events/ AV set up:
Ordering/Receiving (posters & trailers): Additional Super Mario Galaxy posters were delivered in addition to a single Obsession one sheet
Ordering/Receiving (content): Nuke was saved as an MPEG-4 file but cannot be opened, read, or played by any of our applications (I emailed the programmers asking if the filmmakers could resend the content and preferably not via Dropbox download)
Trailer Updates:
Special Events/ AV set up:
Ordering/Receiving (posters & trailers): Additional Super Mario Galaxy posters were delivered in addition to a single Obsession one sheet
Ordering/Receiving (content): Nuke was saved as an MPEG-4 file but cannot be opened, read, or played by any of our applications (I emailed the programmers asking if the filmmakers could resend the content and preferably not via Dropbox download)
Only one canister for Pieces of April was delivered this evening (reels 3-5) and brought up to the 4/6 booth
Outgoing/Shipping (content):
Print/video Inspection:
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Double checked all cues + cross referenced the schedule and initialed for confirmation
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projection cart by entrance?:
Additional Notes:
Outgoing/Shipping (content):
Print/video Inspection:
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Double checked all cues + cross referenced the schedule and initialed for confirmation
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projection cart by entrance?:
Additional Notes: