Projection Admin 8/11
Already have some requests off for September, remember the deadline for requests is Tuesday. Working on the October schedule, too, so the earlier you can get those requests in, the better. Thanks :)
Working on a bit of an overhaul of our HDMI/DVI setups as I plan to setup webcams in Theaters 1, 2, and 3 (and maybe 4) for Zoom Q&A and as a permanent live Q&A recording setup. Will have HDMI-over-ethernet extenders (we refer to them as AJAs but that brand’s version is discontinued) permanently set for 1, 2, & 3 (for Spoons, Kevin Geeks Out, Shouting at the Screen, various stage presentations, and staff meetings), and for cable TV to the Trees projector. Will also use one of the DVI ports on the projectors in each 3 houses to setup the webcam (which can also double as the streaming connection, and could also be repurposed for blu-ray). Ordered all of what we need for Theater 1, and most everything for the other theaters. There will still need to be some variability to different setups but my goal is to eliminate as much cable switching, channel setting adjusting, etc. as possible.
Roger is coming on Tuesday to look at the motor start wiring to the CP500 in Theater 1.
To do this evening/ was completed: We did get the keys for Cliffhanger this morning, but they won't open up until Sunday, so it's looking like we can tech this Monday morning. I notified MOD on the cue sheet.-Alec
Presentation Issues:
Preshow Clips/Playlist: Kat sent over new content today.
Special Events/ AV set up: Fearless will be in T4 instead of T1. I updated the whiteboard in 4/6.
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Ingested New Policy/How To, Blue Beetle 5min PS, Haunting in Venice Trailer, Forecasts 8/18.
Outgoing/Shipping (content):
Print/video Inspection: Print inspection can get done this evening for at least one/two of the prints we received.
Asset tracking doc updated/checked?: Yes! Updated. Added a bunch of titles.
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Adjusted Do the Right Thing, Material Issue (Out of Time) on the cue sheets.
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?:
Projection cart by entrance?:
Additional Notes: