Projection Admin 9/30



To do this evening/ was completed: Staff screenings are out on 7shifts, the LMS and the calendar (fyi FOH meeting means we have one round of screenings on Friday and another on Monday). - L

Cinema meeting went well! We have our first runs for this new week, and we should be getting Brooklyn Dream no later than 10/5 (we followed up with them today). In addition to that, we're just waiting on Attack the Block (which is Sony, so it'll get here a lil down to the wire as per usual), then for the private event on 10/8 Chenelle is still waiting to hear back from the hosts content wise. - L

Friendly reminder there's manual starts in T7 today! - L

Also please fill out the holiday preferences form as soon as you can, thanks!

Presentation Issues:

Preshow Clips/Playlist:

Trailer Updates:

Special Events/ AV set up: Ingested a bunch of ADs/Slides for NewFest and new feature DCPs, one of which we techd today. Desmond, Galen and I techd in T1 and T3 and are updating the spreadsheet as we go. So far so good, only one or two things to check on, everything else is looking great. - L

Updated the Concrete playlist for tomorrow with the special slide.

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content):  Received/ingested The Others.

Ingested feature DCPs OCAP and CCAP of The Social Reckoning to the LMS. 
DCPd and ingested the slide for The Color of Money. 
Started DCPing one of the films (The Birth) for Devilman (double feature screening). This is still transcoding in 4/6. Please ingest once it's done. The other film, The Demon Bird, is downloaded to the preshow/trailers drive if you'd like to DCP that once the other is done. - L

Outgoing/Shipping (content):

Print/video Inspection:

Asset tracking doc updated/checked?:

Maintenance/cleaning: I put some anchors & screws in the 3/7 wall to hang the step ladder, right under the A/C unit

We are still hanging on to the relay for 3/7 since DMS did not end up having the time and supplies to finish this today. I will get another visit scheduled.

Cue sheets updated/checked (every shift): L

Marquee updated?:

Posters updated?:

Cleaning lights on for the night?:

Projection cart by entrance?:

Additional Notes: