NPP Projection Close 11/10
To do this evening/ was completed:
Presentation Issues: The masking in theater 7 seems to have been slightly affected by the projector reset earlier today. I got a call during the final round (Wicker at 9:45PM) that the image was playing on top of the curtains and went down to manually adjust. The curtains seemed stuck in the 1.33 position and would not open up to the film's 1.66 so I opted to bring them to 1.78 to minimize the pillar boxing on the sides of the screen. Thankfully only a few minutes had passed and the rest of the film played without any issues.
Preshow Clips/Playlist: Rescheduled all shows on the LMS for the remainder of this week and the week of 11/13 in theater 7 + added the show playlist for Austin Powers to theater 2 for tomorrow evening's event
Trailer Updates:
Special Events/ AV set up: Red-Headed Woman intro and screening went smoothly + placed the print on its shipping reels, sealed the canisters, and cleaned both projectors following the show (the canisters are at the foot of the stairs in booth 1)
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Keys for feature content in theater 7 were delivered and ingested to the LMS/IMS this evening + a second canister containing the rest of the Castle in the Sky print was delivered and brought to theater 1
Presentation Issues: The masking in theater 7 seems to have been slightly affected by the projector reset earlier today. I got a call during the final round (Wicker at 9:45PM) that the image was playing on top of the curtains and went down to manually adjust. The curtains seemed stuck in the 1.33 position and would not open up to the film's 1.66 so I opted to bring them to 1.78 to minimize the pillar boxing on the sides of the screen. Thankfully only a few minutes had passed and the rest of the film played without any issues.
Preshow Clips/Playlist: Rescheduled all shows on the LMS for the remainder of this week and the week of 11/13 in theater 7 + added the show playlist for Austin Powers to theater 2 for tomorrow evening's event
Trailer Updates:
Special Events/ AV set up: Red-Headed Woman intro and screening went smoothly + placed the print on its shipping reels, sealed the canisters, and cleaned both projectors following the show (the canisters are at the foot of the stairs in booth 1)
Ordering/Receiving (posters & trailers):
Ordering/Receiving (content): Keys for feature content in theater 7 were delivered and ingested to the LMS/IMS this evening + a second canister containing the rest of the Castle in the Sky print was delivered and brought to theater 1
Keys for The Great Muppet Caper were ingested this evening but will not become active until 8AM tomorrow morning
Outgoing/Shipping (content):
Print/video Inspection: Finished inspecting Castle in the Sky and placed everything on house reels
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Adjusted some cues for the week of 11/13 as I was adding the show playlists to the LMS and highlighted the pre-shows in theater 7 with negative flip times + double checked all cues and the schedule for tomorrow
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?: Yes
Projection cart by entrance?: Yes
Additional Notes:
Outgoing/Shipping (content):
Print/video Inspection: Finished inspecting Castle in the Sky and placed everything on house reels
Asset tracking doc updated/checked?:
Maintenance/cleaning:
Cue sheets updated/checked (every shift): Adjusted some cues for the week of 11/13 as I was adding the show playlists to the LMS and highlighted the pre-shows in theater 7 with negative flip times + double checked all cues and the schedule for tomorrow
Marquee updated?:
Posters updated?:
Cleaning lights on for the night?: Yes
Projection cart by entrance?: Yes
Additional Notes: