To do this evening/ was completed:

Presentation Issues:

Preshow Clips/Playlist: Built and scheduled Steal This Story Please for tomorrow.

Trailer Updates:

Special Events/ AV set up: I set out three chairs and two mics in T3 for Being Heumann tonight.
-These hosts also asked me yesterday how many Fidelio devices we have and to test them all before the show. I told them 7 since that's how many headsets we have. While testing this I also ran into some issues and had to do a lot of troubleshooting. Eventually I determined that channel 1 on the T3 Fidelio TX isn't working, so I had to swap things over to channel 2 (which we don't use), after that and updating the audio mapping on the IMS, it finally worked and I got the VI audio. Note that this means you will have to connect to channel 2a (HI) or 2b (VI) for Theater 3. For tonight, the devices circled below are pre-set to 2b since the hosts specified VI. I also tested all 7 headsets.

Turntables are set up for the DJ tonight.

Ordering/Receiving (posters & trailers):

Ordering/Receiving (content): Converted/ingested "Love's Labour's Won" (short film for this month's Pre-Code Parade).

Bela Lugosi Meets a Brooklyn Gorilla is converting to DCP now. Straight to the share folder.

Outgoing/Shipping (content):

Print/video Inspection:

Asset tracking doc updated/checked?:

Maintenance/cleaning: Received the RMA IMS3 from DMS for Theater 6. I wasn't able to make the swap today but I put it in the docking station, set the proper IP address, and uploaded a backup from T6, so it will just be a matter of putting the current drives in and installing it in the projector tomorrow.

Cue sheets updated/checked (every shift):

Marquee updated?: I cleared the 35mm side and put up the FOFIF x Apple rental copy.

Posters updated?:

Cleaning lights on for the night?:

Projection cart by entrance?:

Additional Notes: